Sunday 15 December 2013

KLIA2 ’98% completed’ and ‘on schedule’

http://www.freemalaysiatoday.com/category/business/2013/12/16/klia2-98-completed-and-on-schedule/

KLIA2 ’98% completed’ and ‘on schedule’

The Malaysian Reserve
| December 16, 2013
Deputy Transport Minister Abdul Aziz Karpawi says that the airport will be completed by end of January 2014 and will not tolerate any more delays.
 
By R Kamalavacini

PETALING JAYA: The government will not at any point of time revise the opening date of the first hybrid airport, Kuala Lumpur International Airport 2 (KLIA2) as the main contractors have pledged to deliver it by end of January 2014.

Deputy Transport Minister Abdul Aziz Kaprawi, who heads the KLIA2 taskforce which monitors progress of the multi-billion ringgit project, said from the meeting that he had last Thursday with the management of Malaysia Airports Holdings Bhd (MAHB) and UEM Construction Sdn Bhd-Bina Puri Holdings Bhd joint venture, the main contractor of the terminal building, an assurance has been given that the works will be completed as per schedule.

“Overall, the airport is 98% completed and remaining 2% involves final touch-up works. At the moment, it is behind schedule, however the contractors have one and a half months more to complete the 2% remaining works. So, I don’t see any relevance in another delay to occur,” he told The Malaysian Reserve in a telephone conversation last Friday.

Abdul Aziz was responding to a news report last Friday claiming that KLIA2 will miss its May 2 deadline due to construction issues.

“As long as the contractors deliver the finished project by Jan 31, 2014, the operational readiness and airport transfer (ORAT) process will start from Feb 1, 2014. I am confident everything will be on schedule and will be in place by May 2, 2014. We will not compromise on anymore delays,” he said.

On June 2013, after five delays, MAHB announced April 30, 2014, as the new deadline for completion of the project and set May 2, 2014, as the new operational date of the project.

The current cost for the construction of KLIA2 has increased to RM4 billion from its initial cost of RM2 billion due to change in main airport plan including automation of the baggage handling system and increase in number of customs checkpoints.

The initial project delivery date was 20 months after earthworks began in 2010.

Meanwhile, MAHB in its latest filing to Bursa Malaysia last Friday stated it was monitoring the progress of the KLIA2 construction and expressed concern over the slippage in the work schedule of the main terminal building.

“We reiterated to the terminal building contractor that this project is of national importance and therefore they should make every endeavour to complete on time as committed by them for the May 2, 2014, opening of KLIA2,” it said.

It added that the special taskforce under the purview of Abdul Aziz is also aware of those concerns and is continuing to monitor the construction works “diligently”.

The works on the aeronautical ground lighting and air traffic control systems are progressing on schedule, while the apron, third runway and taxi-way and other infrastructure facilities have been completed, it said.

“The terminal building is scheduled to be completed together with the certificate of completion and compliance (CCC) by end of January 2014, to enable ORAT to commence for three months before the opening date of May 2, 2014,” MAHB said.

KLIA2 is built to be Malaysia’s new international airport hub, that allows seamless connectivity for both local and international low-cost plus full service carriers.

The new terminal measures about 257,000 sq m, with 60 gates, eight remote stands, 80 aerobridges, plus a retail space of 32,000 sq m to accommodate 225 retail outlets and designed to cater to 45 million passengers a year with a built cost of around RM4 billion.

The existing low-cost terminal catered to 19 million passenger traffic in 2012 while the main terminal at KLIA, 39.9 million, the company’s website revealed.

This content is provided by FMT content provider The Malaysian Reserve

Monday 7 October 2013

MALINDO lands on KLIA Runaway 3


Runway in delayed KLIA2 airport won’t sink, assures Hishamuddin
BY YISWAREE PALANSAMY
October 07, 2013
A Malindo Air plane makes a succesful trial landing on runway 3 at KLIA2 in Sepang, this morning. – The Malaysian Insider pic by Nazir Sufari, October 7, 2013.A Malindo Air plane makes a succesful trial landing on runway 3 at KLIA2 in Sepang, this morning. – The Malaysian Insider pic by Nazir Sufari, October 7, 2013.




Acting Transport Minister Datuk Seri Hishamuddin Hussein today gave assurance that the new runway at the Kuala Lumpur International Airport 2 (KLIA 2) will not sink.

"We know we are not perfect, but we are on track," he said.

The third runway project at the new terminal for low-cost carriers has been shrouded in controversy after several members of the opposition alleged that the runway risked sinking due to shoddy work.

"There is always cynicism in what we do, especially from the alternative media," Hishamuddin, who is also the Defence Minister, said.

He added such remarks do not do justice "to people who worked hard to show probably something unique in the region".

"If our runways sink, we would not have retained our seat in the International Civil Aviation Organisation (ICAO) for our professionalism.

"It is not an easy feat to accomplish," he told a press conference after witnessing the trial landing of the first commercial aircraft Malindo Air Boeing 737-900ER on the third runway.

However, Hishamuddin did not say when KLIA 2 would start operations.

"I see that those involved in this are taking their tasks seriously and I hope the project can be completed in May at no additional cost," he said, noting that there is more work to be done.

"I do not want to talk about the vision for KLIA 2 until what we hope for is completed. There are many challenges ahead and it is important to not put vision first until we complete this," he added.

In September last year, the Public Accounts Committee (PAC) said it would look into Khazanah Nasional Berhad's role in the delays and rising costs of the KLIA 2 project, as well as in the share swap involving Malaysia Airlines (MAS) and AirAsia led to a RM20 million anti-trust fine.

PAC chairman Datuk Nur Jazlan Mohamed said the committee would investigate the roles of consultants and merchant bankers in these deals although both MAS and Malaysia Airports Holding Berhad (MAHB) are public-listed companies, with state asset manager Khazanah as the main shareholder.

The KLIA 2 project was initially budgeted at RM1.6 billion but the cost ballooned to RM4 billion after several amendments.

The new airport was initially slated to open in September 2011 but the date has since been delayed five times. It is now expected to be ready in May next year.

According to media reports, MAHB received 230 non-compliance reports for the new terminal, including cracks in the buildings as well as ceilings which were built too low, requiring them to be torn down and rebuilt. - October 7, 2013.